Post date: 12/23/2014 1:13 pm

Indian Trail has been opened to traffic using one lane in each direction between IL-31 and IL-25.  The road is scheduled to be open from now until March 2nd of 2015, when it will be closed again for the reconstruction of the West bridge over the Fox River.  The Conractor has completed a significant amount of work for the new East bridge over the Fox River.  D Construction plans to complete the East Bridge's parapet / railing features during the Winter as weather permits.   Expect to see construction activity on the outer portions of the bridges throughout the Winter months, which may cause

Post date: 12/5/2014 10:28 am

D Construction was able to successfully pour the east bridge deck over the Fox River!  Upon the bridge deck concrete completing the required one week curing period, the Contractor will focus on completing the new 7' wide sidewalks, parapet walls / railings and bridge related lighting, weather permitting.  D Construction will still be able to work during the curing period in preparation for the completing the remaining items.  The current schedule includes opening Indian Trail, between IL-31 and IL-25, with one lane in each direction by December 24th, weather permitting.  Please anticipate

Post date: 11/18/2014 12:23 pm

The project has encountered some recent challenges that have impacted the schedule.  The challenges are associated with the Contractor’s ability to place concrete due to a cement shortage within the concrete industry and an unseasonably cold November.  The remaining key project tasks (bridge deck, sidewalk and parapet) associated with the east bridge over the Fox River rely on the ability to pour concrete.  The Contractor has been working diligently to avoid further problems related to the cement shortage.  The Contractor plans to proceed with placing concrete for the remaining items when

Post date: 11/10/2014 1:49 pm

The new east bridge deck over the Fox River is framed and reinforcement steel is being installed in preparation to pour the concrete structure.  The east bridge deck will contain over 140,000 pounds of reinforcement steel.  Following the bridge deck pour will be the installation of the approach pavement (transition of pavement between the bridge deck and the roadway), 7' sidewalks along the bridge and decorative bridge railing.

Post date: 10/18/2014 11:12 am

D Construction completed replacing all of the existing beam bearings at abutment and pier locations for the east bridge over the Fox River.  The existing beams have been lowered down on the new bearings and all new structural steel beams have been set in their final positions.  As all of the substructure components have been completed, the Contractor has started framing and form work for a new widened concrete bridge deck.  Once D Construction completes the bridge deck form work, reinforcement steel will be installed and the deck will be ready to be poured.